We were awarded the contract to manufacture and deliver the precast units for UB86 on the Cherryville to Kilkenny line by Irish Rail – consisting of a single precast deck unit, ballast retainer units and cill beams.

Due to the typical size of these deck units they are usually precast in segments and then stitched together on site. However we manufactured the entire deck unit in one single piece thus allowing it to be delivered and erected on the same night during a single rail possession. This also eliminated insitu stitching works and the associated delays due to curing time required.

The precast deck unit measured 20.4 meters long and 4.4 meters wide, weighing over 115 tonnes. Special equipment was required to transport the unit to site and our long-standing transport partners Whitten Road Haulage ensured the timely delivery for the rail possession.

Project Details

CLIENT
Irish Rail

CONTRACTOR
Coffey Construction